Baseline question
![]()
Hi,
can i include a change set source file in an already created baseline. Example: 1. We deployed to production and baseline 1 (BL1) was created 2. There is an emergency fix in one of the component 3. developers will fix the code and checkin and deliver the code 4. we want to include this change set in the same Baseline as BL1 Do we have to remove the already created Baseline BL1 and than reapply the BL1 or we can overwrite the Baseline BL (i.e create a Baseline again on BL1) what is the good practice. Thanks |
2 answers
![]()
When documenting baseline for other people to retrieve files from be sure you also document the number the baseline gets. I would also document the text description of the baseline as well however the text in this field can be duplicated. For example:
32: Release 1.2.3.4 45: Release 1.2.3.4 Are two totally different baselines. I wish it wasn't allowed to have duplicate text descriptions. |