Can Product Backlog be exported from 4.0.6 and imported into 6.0?

We want to manage a Scrum project using RTC 6.0.  However, we currently only have RTC 4.0.6 installed, and it will be a couple weeks before we have 6.0 installed.   Can we create our project and set up our product backlog with the associated Stories, Work Items, and Tasks in RTC 4.0.6 right now, and start using it to deliver the project, and then somehow move it all over to our new RTC 6.0 environment once that gets built?

I am not talking about source code, only the Scrum project management artifacts mentioned above.

0 votes



One answer

Permanent link
hi john,
Once the 6.0 server is stood up, following the interactive upgrade guide will migrate all the data from the 4.0.6 to the 6.0 server.  However moving the artifacts manually will be rather painful, and the work item numbers will most  likely change...meaning any links between the workitems may break.  

-Abraham

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,220
× 267
× 173
× 74
× 14

Question asked: Jul 10 '15, 12:11 p.m.

Question was seen: 3,531 times

Last updated: Jul 10 '15, 1:59 p.m.

Confirmation Cancel Confirm