Restricted Access to Workitems
Hi
The following URL is of great help to restrict access to Work Items. http://jazz.net/library/article/554/ However, there seems to be a limitation. I have a Main Project Area and 6 Different Project Areas for Restricted access for 6 Teams. Now, I want to restrict access to a Work Item to 2 teams. How can I do that? Regards Shubjit |
Accepted answer
Geoffrey Clemm (30.1k●3●30●35)
| answered Apr 06 '11, 11:15 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
You cannot do this currently.
Work item 102270 asks for this support. Please feel free to add a comment to indicate your interest/support. Cheers, Geoff On 4/6/2011 11:38 AM, shubjit wrote: Hi Shubjit Naik selected this answer as the correct answer
|