Generate a SLA date dependant on the priority & creation


John S F Lander (901941) | asked Mar 21 '11, 10:13 a.m.
Is there a ways to generate a SLA date dependant on the priority set on a record, so that we can set the queries on a dashboard to identify this information

One answer



permanent link
Ralph Schoon (63.1k33646) | answered Mar 22 '11, 5:05 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Hi John,

since 3.0 there is a way to create dependant attributes as well as default value provider. I believe you could use that to generate a date value as requested below.

Ralph

Is there a ways to generate a SLA date dependant on the priority set on a record, so that we can set the queries on a dashboard to identify this information