James Labrie (18123818) | asked Dec 21 '10, 3:42 a.m.
Hi,

Version :RTC 2.0.0.2 ifix5
I have two questions about Planned Items view.

Q1.
When I try to put "Estimate" or "Time Spent", I can select "30 minuts, 1 hour, 2hour, 4hour, 1 day" and so on.

Are the values customizable like "30 minuts, 1 hour, 2hour, 3hour, 4hour, 5hour ..." ?


Q2.
As far as I know, in RTC 3.0, it is possible to set "Due Date" on Planned Items view without opening the workitem.(Calender is shown.)
But as far as I have checked, it is not possible in RTC 2.0.0.2.
Is there a way to make it possible in RTC 2.0.0.2 ?


Regards
James

One answer



permanent link
Benjamin Chodroff (8985231) | answered Jan 14 '11, 5:45 p.m.
Q1: Just enter in 5 m for 5 minutes or 1h for 1 hour, 1 d for 1 day, etc.

Q2: Not easily, but you could edit the plan presentation and have that be configured to be displayed, I believe.