Question about Planned Items view
Hi,
Version :RTC 2.0.0.2 ifix5 I have two questions about Planned Items view. Q1. When I try to put "Estimate" or "Time Spent", I can select "30 minuts, 1 hour, 2hour, 4hour, 1 day" and so on. Are the values customizable like "30 minuts, 1 hour, 2hour, 3hour, 4hour, 5hour ..." ? Q2. As far as I know, in RTC 3.0, it is possible to set "Due Date" on Planned Items view without opening the workitem.(Calender is shown.) But as far as I have checked, it is not possible in RTC 2.0.0.2. Is there a way to make it possible in RTC 2.0.0.2 ? Regards James |
One answer
Q1: Just enter in 5 m for 5 minutes or 1h for 1 hour, 1 d for 1 day, etc.
Q2: Not easily, but you could edit the plan presentation and have that be configured to be displayed, I believe. |