Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

Formal Project Management RTC v3

Hi,
I'm trying RTC v3 Formal Management Process.
I planned two tasks WorkItems (let's say A and B).
Both of them have been set as ASAP Constraint Type.
A is the predecessor of B.
A is Closed (and Fixed).
If I StartWork on B (set as Work In Progress State) I catch the following warning: Work item is started before its predecessor work item is complete (see the image below).

How to avoid this warning ?

Thanks in advance,
Marco

Screenshot:
http://stodelat.files.wordpress.com/2010/09/taskdependency.jpg

0 votes



5 answers

Permanent link
Your screen shot was clipped at a point which might be interesting ...
the red-outlined item is a predecessor of another item (off the screen)
.... what is the state of that off-screen item?

Cheers,
Geoff

On 12/2/2010 4:23 AM, primeur.jazz.net wrote:
Hi,
I'm trying RTC v3 Formal Management Process.
I planned two tasks WorkItems (let's say A and B).
Both of them have been set as ASAP Constraint Type.
A is the predecessor of B.
A is Closed (and Fixed).
If I StartWork on B (set as Work In Progress State) I catch the
following warning: Work item is started before its predecessor work
item is complete (see the image below).

How to avoid this warning ?

Thanks in advance,
Marco

Screenshot:
http://stodelat.files.wordpress.com/2010/09/taskdependency.jpg

0 votes


Permanent link
Hi Geoff,
sorry I didn't see that the screenshot had been cut!

Try and see the complete screenshot on http://stodelat.files.wordpress.com/2010/09/taskdependency.jpg

Thanks,
Marco




Your screen shot was clipped at a point which might be interesting ...
the red-outlined item is a predecessor of another item (off the screen)
.... what is the state of that off-screen item?

Cheers,
Geoff

On 12/2/2010 4:23 AM, primeur.jazz.net wrote:
Hi,
I'm trying RTC v3 Formal Management Process.
I planned two tasks WorkItems (let's say A and B).
Both of them have been set as ASAP Constraint Type.
A is the predecessor of B.
A is Closed (and Fixed).
If I StartWork on B (set as Work In Progress State) I catch the
following warning: Work item is started before its predecessor work
item is complete (see the image below).

How to avoid this warning ?

Thanks in advance,
Marco

Screenshot:
http://stodelat.files.wordpress.com/2010/09/taskdependency.jpg

0 votes


Permanent link
Still shows up as clipped when I view it.
Note that I'm interested in the third line (i.e. the line below the one
with the red mark and error message).

Cheers,
Geoff

On 12/3/2010 5:53 AM, primeur.jazz.net wrote:
Hi Geoff,
sorry I didn't see that the screenshot had been cut!

Try and see the complete screenshot on
http://stodelat.files.wordpress.com/2010/09/taskdependency.jpg

Thanks,
Marco




gmclemmwrote:
Your screen shot was clipped at a point which might be interesting
..
the red-outlined item is a predecessor of another item (off the
screen)
.... what is the state of that off-screen item?

Cheers,
Geoff

On 12/2/2010 4:23 AM, primeur.jazz.net wrote:
Hi,
I'm trying RTC v3 Formal Management Process.
I planned two tasks WorkItems (let's say A and B).
Both of them have been set as ASAP Constraint Type.
A is the predecessor of B.
A is Closed (and Fixed).
If I StartWork on B (set as Work In Progress State) I catch the
following warning: Work item is started before its predecessor work
item is complete (see the image below).

How to avoid this warning ?

Thanks in advance,
Marco

Screenshot:
http://stodelat.files.wordpress.com/2010/09/taskdependency.jpg

0 votes


Permanent link
Geoff,
the error message is about its predecessor (NOT about the successor).
BTW the complete screenshot URL is:
http://stodelat.files.wordpress.com/2010/12/reqplan-complete1.jpg

Thanks,
Marco

0 votes


Permanent link
Understood about what the error message said.
I did have some issues with pre-release versions of those features where
the error message was wrong/misleading, and just wanted to make sure
that wasn't the case here.

Unfortunately, the full screenshot did not show me anything that looked
wrong, so I don't have any ideas on what might be happening here.
You'll probably want to engage with Rational support on this one.

Here are some things to play with:
- Try removing that predecessor dependency, and verify this fixes the
error message.
- Try transitioning the predecessor to some other "complete" state
(perhaps a "validated" state?).
- Try re-opening the predecessor, and then completing it again (in case
there is some stale cached state in the web server).
- Refresh your browser page between each operation.
- Look at those other errors on that page ... are they the same message?

Cheers,
Geoff

On 12/6/2010 9:53 AM, primeur.jazz.net wrote:
Geoff,
the error message is about its predecessor (NOT about the successor).
BTW the complete screenshot URL is:
http://stodelat.files.wordpress.com/2010/12/reqplan-complete1.jpg

Thanks,
Marco

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Dec 02 '10, 4:19 a.m.

Question was seen: 7,121 times

Last updated: Dec 02 '10, 4:19 a.m.

Confirmation Cancel Confirm