Planned Snapshot not taking 'Constraint' dates
Hi All,
I have a the workitems created in a Formal template. Parents are Milestones and childs are tasks.
Parent 1
-Child 1.1 ,Est 0 secs,SNET 30/09/2013
-Child 1.2, Est 1 week,SNET 30/09/2013,Predecessor Child 1.1
-Child 1.3,Est 1 week,SNET 7/10/2013,Predecessor Child 1.2
Parent 2
-Child 2.1,Est 6 weeks, SNET 30/09/2013, Predecessor Child 1.1
-Child 2.2, Est 2 weeks,SNET 30/10/2013,Predecessor Child 1.1
-Child 2.3, Est 2 weeks,SNET 30/09/2013, Predecessor Child 1.1
I take a planned snapshot now.
Result :
Est Planned Start date Planned End date
Child 1.1 0 secs 10-Oct-2013 9:03:56 AM 10-Oct-2013 9:03:56 AM
Child 1.2 1 week 10-Oct-2013 9:03:56 AM 17-Oct-2013 9:03:56 AM
Child 1.3 1 week 17-Oct-2013 9:03:56 AM 24-Oct-2013 9:03:56 AM
Child 2.2 2 weeks 10-Oct-2013 9:03:56 AM 24-Oct-2013 9:03:56 AM
Child 2.3 2 weeks 10-Oct-2013 9:03:56 AM 24-Oct-2013 9:03:56 AM
Expected :
Est Planned Start date Planned End date
Child 1.1 0 secs 30-Sep-2013 9:00:00AM 30-Sep-2013 9:00:00 AM
Child 1.2 1 week 30-Sep-2013 9:00:00AM 7-Oct-2013 5:00:00 PM
Child 1.3 1 week 7-Oct-2013 9:00:00AM 14-Oct-2013 5:00:00 PM
Child 2.2 2 weeks 30-Sep-2013 9:00:00AM 14-Oct-2013 5:00:00 PM
Child 2.3 2 weeks 30-Sep-2013 9:00:00AM 14-Oct-2013 5:00:00 PM
Ideally the planned start date should consider the Constraint date correct ? and also all these tasks are unassigned. I am not sure why the dates are populating incorrectly as well.
We are using RTC 4.0.
Can someone help me with the same ?
Thanks!
|
Accepted answer
Hi Varun
varun ibm selected this answer as the correct answer
Comments 1
varun ibm
commented Oct 10 '13, 4:41 a.m.
Hi Aradhya, Thank you for explanation as of how the snapshots are calculated. Just one question.
So if I need to populate the Planned Start and End Dates as per the constraint dates, then I need to plan in Advance. Correct ? because it will not work for past days.
1
Hi Varun
Yes its better to take the first plan snapshot before your Iteration starts. That way you will get the planned dates that are calculated the way you want.
varun ibm
commented Oct 11 '13, 5:53 a.m.
Thanks! |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.