Rollup TimeSpent into Parent Work item
We typically work in an environment where a defect is decomposed into a number of child tasks. In order to get a truly accurate figure of the time spent against the defect, I would have to sum up the time spent in all the individual child tasks. Is there a way to roll-up the time spent for all child work items into the parent while writing a query?
|
2 answers
Ralph Schoon (63.1k●3●36●45)
| answered Jul 30 '12, 5:36 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Sorry for the late reply. You would need to create a follow up action / participant similar to the one described in the RTC Extensions workshop in the Library.
|
Hi Rahul
Thanks
Aradhya K
|