Task Dependencies Do Not Update When New Tasks Inserted
I have noticed that when a new task is added or a task is modified such that it will impact the start time of follow on tasks, these follow on task must be updated manually to reflect a change in the schedule. Is there a way around this issue or is it in queue to be addressed?
|
One answer
Geoffrey Clemm (30.1k●3●30●35)
| answered Mar 05 '10, 2:23 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Enforcing inter-task dependencies is something that the "Rational
Project Conductor" project is responsible for. See https://jazz.net/projects/rational-project-conductor/ Cheers, Geoff arober wrote: I have noticed that when a new task is added or a task is modified |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.