How to establish and maintain traceability links between requirements, work items, and other artifacts using IBM DOORS Next Generation and IBM Rational Team Concert
Hi Team,
We are using CLM 7.0.2 SR1 . Without using global configuration, how we would establish and maintain traceability links between requirements, work items, and other artifacts using IBM DOORS Next Generation and IBM Rational Team Concert
Thanks |
One answer
Ralph Schoon (63.5k●3●36●46)
| answered Jun 28 '23, 7:02 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER You add associations in the project areas you want to link between: https://www.ibm.com/docs/en/engineering-lifecycle-management-suite/lifecycle-management/7.0.2?topic=client-adding-associations
Once you did it, you can link items using the editors Link areas/sections.
|