Global Configuration for every release - Concept and Problems
(Sorry for the long post. It cannot be said short.)
While the requirements are being defined in DNG, project RTC admin starts creating release iterations eg: RTC_AB190 in the RTC timeline and associates the development GC to the iteration in the RTC releases section (This activity take place even before the requirements are complete). The project manager starts creating the RTC stories from requirements and assigns to the project backlog iteration. The backlog iteration is associated to the development GC. After the requirements are frozen and a releases GC has been created as described in the step 1 above the corresponding RTC work items are moved from the backlog iteration to the release iteration !. Also the development GC is replaced by the release GC in the RTC releases section for this iteration.
STEP 3: Integration and Verification – Complete verification activity, baseline RQM and replace the RQM stream in the release GC.
The integration and verification activities are carried out on the baselined requirements for release GC – AB1910. The testcases are linked to the requirements using this GC. Once the verification activities are completed a baseline is created eg: BL_RQM_AB1910. This baseline replaces the RQM stream in the release gc.
Problem: From Step 2: RTC work items are moved from the backlog iteration to the release iteration
As the RTC work items are moved from the backlog iteration (which was associated to the development GC – AB_Development) to the release GC – AB1910 the traceability links also moves to the release gc leading to the following situation:
A full view of the RTC In progress/ implemented work items from the development eg: GC – AB_Development is not posible. The RTC work items are distribute to several release GCs. So a consolidated report of the project status from a single GC is not possible. Is it possible to get a full view of RTC work item status from a single gc (Ideal is from development as the traceability links were first established) instead of several release gcs?.
Please help to review our concept and guide us out of this situation.
<o:p> </o:p>
<o:p> </o:p>
One answer
Are "GC – AB1910" and "GC – AB_Development" different Global Components?
Why are you associating Release Iteration RTC_AB190 to the Development GC?
If not, then exists no reason to associate the Backlog Iteration to any GC.
If yes, then you seem to (mis-)use the Backlog Iteration as a Development Iteration.
As the RTC work items are moved from the backlog iteration (which was associated to the development GC – AB_Development) to the release GC – AB1910 the traceability links also moves to the release gc ...
- Which tracability links?
- Who moves the tracability links?
A full view of the RTC In progress/ implemented work items from the development eg: GC – AB_Development is not posible.