ClearCase to Team Concert being blocked by rebase operation
We are trying to run a second synchronization on an existing ClearCase Synchronization stream. We are going only from CC to RTC. The last successful syncronization was Sept 27th. There have been several baselines on the components since then The sync process appears to be trying to rebase the CC sync stream.
Problem running 'synchronizeStream':
Synchronization blocked by error: javax.wvcm.WvcmException: CRRTC4061E: The synchronization process cannot be completed. The "cleartool" command completed with a non-zero status or error message: cleartool rebase -view DO_NOT_USE_edsp_Delta_main_Int -stream oid:94075f44.23f94120.b735.4e:a0:75:1c:81:f7@vobuuid:5e88c7eb.3fc14616.ab18.d6:74:e0:83:b1:9a -baseline baseline:edsp_Delta_main_10_1_2018.7346@\edsp_em_pvob2,baseline:edsp_Delta_main_10_24_2018.6924@\edsp_em_pvob2,baseline:edsp_Delta_main_10_24_2018.6921@\edsp_em_pvob2,baseline:edsp_Delta_main_10_1_2018.582@\edsp_em_pvob2,baseline:edsp_Delta_main_10_24_2018.98@
...
\edsp_em_pvob2,baseline:edsp_Delta_main_10_24_2018.432@\edsp_em_pvob2 -complete
cleartool: Error: Can't rebase to baseline "edsp_Delta_main_10_24_2018.7022" of component "CO" because it was created in this stream. cleartool: Error: Can't rebase to baseline "edsp_Delta_main_10_24_2018.7025" of component "CP" because it was created in this stream. cleartool: Error: Can't rebase to baseline "edsp_Delta_main_10_24_2018.7028"
...
Why is it even trying to rebase the integration stream? How do we get it to stop?
Using CC 8.0.1 and RTC 6.0.2. Both on Windows.
|
Be the first one to answer this question!
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.
Comments
To confirm, when you say "we are going only from ClearCase to RTC", that means that you are running in "import-only" mode, is that right? If so, are you doing a "selective import" (where you specify which baselines you want to import), or all baselines?
Disclaimer: It's been a long time since I've done anything with CC synchronization, and I no longer have ClearCase on my machines, so cannot experiment ... so I'm just working from memory here.