How to copy test cases from one RQM project to another
I am using version 6.0.5
How can I copy test cases from one RQM project to another
|
Accepted answer
You will need to use the RQMCopyUtility - More information pertaining to it is available at - Brief Summary about RQMCopyUtility -This can be used to copy RQM artifacts such as Test Plans, Test Cases, Lab Resources, etc. The destination of the copy can be the same Project Area, a different Project Area in the same Rational Quality Manager repository, or a different repository/server altogether. Its meant to share common artifacts across projects and teams. It is not intended as a back-up utility Pankaj Sharma selected this answer as the correct answer
|
One other answer
Please note, that it might much easier to use the built in "Duplicate" function.
You can either "Duplicate" a test case from within the current test case ("Duplicate" button in the upper right), or you can browse test cases, multi select test cases, and then do a batch copy (action menu at the beginning of the line).
Also the linked test script is copied.
But be aware, that you have to consider different attributes.
You have now complete independent test cases … there is no synchronization mechanism between copied test artifacts.
See also online help https://jazz.net/help-dev/clm/index.jsp?re=1&topic=/com.ibm.rational.test.qm.doc/topics/c_copy_overview.html&scope=null