What is the impact of stopping a full dcc job?


Michael Alberda (2311648) | asked Aug 27 '18, 4:28 a.m.
Hi,

I have an issue whereby a team member accidentally started a full dcc load for RTC, the problem is that it runs for far too long. What will the impact be if I stop the job and then run a delta load or do I need to wait for the full load to now finish?

Thanks,
Regards,
Michael.

One answer



permanent link
Rafik Jaouani (5.0k16) | answered Aug 27 '18, 3:40 p.m.
JAZZ DEVELOPER

You can stop the job, but you will need to manually set the 'Delta Load since date' value for each affected resource group.