It's all about the answers!

Ask a question

What is the impact of stopping a full dcc job?


Michael Alberda (2311447) | asked Aug 27 '18, 4:28 a.m.
Hi,

I have an issue whereby a team member accidentally started a full dcc load for RTC, the problem is that it runs for far too long. What will the impact be if I stop the job and then run a delta load or do I need to wait for the full load to now finish?

Thanks,
Regards,
Michael.

One answer



permanent link
Rafik Jaouani (5.0k16) | answered Aug 27 '18, 3:40 p.m.
JAZZ DEVELOPER

You can stop the job, but you will need to manually set the 'Delta Load since date' value for each affected resource group.

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.