RTC Planning - no progress of any tasks is being presented
Oran Erez (11●1)
| asked Aug 30 '17, 2:32 a.m.
edited Aug 30 '17, 4:07 a.m. by Ralph Schoon (63.6k●3●36●46) Hi, My RTC Planning for exists or new plans does not show any progress of the tasks even after user is updating the 'time spent' field. I was able to see it works once but that was only single time and ever since it was working. No changes have been made in Configuration date of the project area in respect to Planning other than what was required and it was seen working. Be glad if anyone observe the same issue and can recommand what can be done to retrive this basic fuctioanility of planning to track progress within. Thank you. |
Be the first one to answer this question!
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.
Comments
Please read
How should I ask a question in the Forum if I want to receive useful answers?
Also note that planning requires the correct configuration of
- Timelines and iterations including start an end dates - relative to the current time/date
- Association of team and project areas to said timelines
- Current iteration being set
- Allocation of team members to said project/team areas with percentage
See https://jazz.net/library/article/594 for some introduction and maybe provide some more information as mentioned above.