Why is the error "Deferred Operation failed" seen while executing a TSER?

I have very simple structure of Test Plan -> Test Suite -> Test Case -> Test script. When I execute the Test case directly, it is working perfectly. But when I execute the Test Suite through a TSER, I get the error "Deferred Operation failed". I read that this error is seen sometimes when Approval Tracking is setup in a PA but I do not have any setup in my PA. What else could be the reason?

0 votes


Accepted answer

Permanent link

Hi Maria,

Given the behavior reported, it seems to be specific to RQM Test Suites. You could be hitting a defect.
Please raise a PMR with IBM support.

For starters, gather firebug data to see if a valid error condition is reached on the tool as per technote below:
http://www-01.ibm.com/support/docview.wss?uid=swg21657804

Best Regards
Sunil

Ralph Schoon selected this answer as the correct answer

0 votes


One other answer

Permanent link

Thanks for your response, Sunil.
I have already raised the PMR and it has been identified as a Sev1 defect and escalated.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Aug 11 '17, 3:30 a.m.

Question was seen: 3,245 times

Last updated: Aug 21 '17, 9:18 a.m.

Confirmation Cancel Confirm