How to create a quick query in an RTC Plan that colorizes work items with timeSpent>estimate?
It seems useful to highlight work items on a plan for which time spent is greater than the effective estimate for the work item. Using RTC quick query syntax (https://www.ibm.com/support/knowledgecenter/SSYMRC_6.0.3/com.ibm.team.apt.doc/topics/r_quick_query_syntax.html), I can find and colorize a work item based on comparisons between timeSpent and a value, and between estimate and a value. But, it appears that the very useful comparison between timeSpent and estimate isn't available to me.
|
One answer
looking at the doc this doesn't seem possible (https://www.ibm.com/support/knowledgecenter/SSYMRC_6.0.3/com.ibm.team.apt.doc/topics/r_quick_query_syntax.html)
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.