Is it possible to mark more than 1 iteration as the Current Iteration at any given time? Reason I ask is because our Iterations overlap a little so for about a week they're both considered current.

One answer



permanent link
Ryan Manwiller (1.3k1) | answered Sep 03 '09, 5:54 p.m.
JAZZ DEVELOPER
No, you can only have 1 current iteration per timeline.

If you want more than one, you'd need to have multiple timelines.

---