is there a formal mechanism to bring a CCM project under a Lifecycle project?


sam detweiler (12.5k6189201) | asked Jan 16 '14, 6:06 a.m.
for a couple of our teams we created a project in RTC.   But now they want the RM/QM components of a lifecycle project.

is there a mechanism to do that?  Otherwise this is another scenario for my copy project utility.
create a CLM project, migrate contents from outside to the CCM project

Accepted answer


permanent link
Lauren Hayward Schaefer (3.3k11427) | answered Jan 16 '14, 7:08 a.m.
JAZZ DEVELOPER
Hi Sam,

It is possible to add existing project areas to a lifecycle project.  See https://jazz.net/help-dev/clm/index.jsp?re=1&topic=/com.ibm.jazz.platform.doc/topics/c_creating_managing_cross_application_projects.html&scope=null for more information.
sam detweiler selected this answer as the correct answer

Comments
sam detweiler commented Jan 16 '14, 7:37 a.m.

Thank you SO much for that link!!.. 


Lauren Hayward Schaefer commented Jan 16 '14, 7:41 a.m.
JAZZ DEVELOPER

You're welcome! :-)

Your answer


Register or to post your answer.