Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

RQM version of RTC "Plan snapshots"

CLM 502,

Hello,

In RTC, you can make a snapshot of a plan and then compare two snapshots to see how work items were modified, removed or added to the plans. Is there anything similar for RQM?

Is there a way for me to see how much testing or modification of tests were done from Monday to Monday...or something like this? Looking more for point of time type of data.

thanks

0 votes



One answer

Permanent link
Once you turn on configuration management, you can create a baselines for the plan configurations you want to compare (but you have to create the baseline when the project is in that state ... you cannot go back and create a baseline for some arbitrary earlier time).

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,019
× 7,495
× 239
× 21

Question asked: Dec 22 '16, 9:20 a.m.

Question was seen: 3,538 times

Last updated: Dec 22 '16, 11:37 a.m.

Confirmation Cancel Confirm