Mahari Hill (4861184230) | asked Dec 22 '16, 9:20 a.m.
CLM 502,

Hello,

In RTC, you can make a snapshot of a plan and then compare two snapshots to see how work items were modified, removed or added to the plans. Is there anything similar for RQM?

Is there a way for me to see how much testing or modification of tests were done from Monday to Monday...or something like this? Looking more for point of time type of data.

thanks

One answer



permanent link
Geoffrey Clemm (30.1k33035) | answered Dec 22 '16, 11:37 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Once you turn on configuration management, you can create a baselines for the plan configurations you want to compare (but you have to create the baseline when the project is in that state ... you cannot go back and create a baseline for some arbitrary earlier time).