Incorrect date is taking in RTC import
![]()
I am having an issue while update workitems in RTC CLM 5.0. tool is taking different date than given in .csv
|
One answer
![]()
Ralph Schoon (61.8k●3●36●43)
| answered Dec 01 '16, 2:18 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
You can not import or modify calculated dates, especially not:
|
Comments
Which attribute? Is the time correct based on the server timezone?
All date/time field like creation date, modified date, Actual Roll on date, Roll on submission date. I took .csv from eclipse client modified it (formatting) and then tried to import it. it is taking some other date.