Incorrect date is taking in RTC import
I am having an issue while update workitems in RTC CLM 5.0. tool is taking different date than given in .csv
|
One answer
Ralph Schoon (63.5k●3●36●46)
| answered Dec 01 '16, 2:18 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
You can not import or modify calculated dates, especially not:
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.
Comments
Which attribute? Is the time correct based on the server timezone?
All date/time field like creation date, modified date, Actual Roll on date, Roll on submission date. I took .csv from eclipse client modified it (formatting) and then tried to import it. it is taking some other date.