Incorrect date is taking in RTC import

I am having an issue while update workitems in RTC CLM 5.0. tool is taking different date than given in .csv

0 votes

Comments

 Which attribute? Is the time correct based on the server timezone?

All date/time field like creation date, modified date, Actual Roll on date, Roll on submission date. I took .csv from eclipse client modified it (formatting) and then tried to import it. it is taking some other date.



One answer

Permanent link
 You can not import or modify calculated dates, especially not:
  • Creation Date
  • Modification Date
  • Dates calculated by plans

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Nov 30 '16, 7:50 a.m.

Question was seen: 1,879 times

Last updated: Dec 01 '16, 2:18 a.m.

Confirmation Cancel Confirm