It's all about the answers!

Ask a question

Incorrect date is taking in RTC import


sousan hussain (291254) | asked Nov 30 '16, 7:50 a.m.
I am having an issue while update workitems in RTC CLM 5.0. tool is taking different date than given in .csv

Comments
Ralph Schoon commented Nov 30 '16, 8:37 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

 Which attribute? Is the time correct based on the server timezone?


sousan hussain commented Dec 01 '16, 12:07 a.m. | edited Dec 01 '16, 2:17 a.m.

All date/time field like creation date, modified date, Actual Roll on date, Roll on submission date. I took .csv from eclipse client modified it (formatting) and then tried to import it. it is taking some other date.

One answer



permanent link
Ralph Schoon (63.5k33646) | answered Dec 01 '16, 2:18 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
 You can not import or modify calculated dates, especially not:
  • Creation Date
  • Modification Date
  • Dates calculated by plans