It's all about the answers!

Ask a question

Incorrect date is taking in RTC import


sousan hussain (29754) | asked Nov 30 '16, 7:50 a.m.
I am having an issue while update workitems in RTC CLM 5.0. tool is taking different date than given in .csv

Comments
Ralph Schoon commented Nov 30 '16, 8:37 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

 Which attribute? Is the time correct based on the server timezone?


sousan hussain commented Dec 01 '16, 12:07 a.m. | edited Dec 01 '16, 2:17 a.m.

All date/time field like creation date, modified date, Actual Roll on date, Roll on submission date. I took .csv from eclipse client modified it (formatting) and then tried to import it. it is taking some other date.

One answer



permanent link
Ralph Schoon (63.1k33646) | answered Dec 01 '16, 2:18 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
 You can not import or modify calculated dates, especially not:
  • Creation Date
  • Modification Date
  • Dates calculated by plans

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.