It's all about the answers!

Ask a question

Linking tasks to new/other Plans in CCM


William Prioleau (112) | asked Oct 20 '16, 11:28 a.m.
 Haw can I link an old task in 'plan A' to a new plan or sprint?

One answer



permanent link
Don Yang (7.7k21109138) | answered Oct 20 '16, 6:42 p.m.
Hi, WIlliam

If Plan A and new plan are in a same project area, drag and drop between plan feature applies:

http://www.ibm.com/support/knowledgecenter/SSYMRC_6.0.0/com.ibm.team.apt.doc/topics/t_modifying_work_items_in_an_iteration_plan.html

Some other discussions may help:
https://jazz.net/forum/questions/159633/how-to-move-work-items-accross-the-plans

There may other similar discussions in Forum depending on the scenarios.

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.