William Prioleau (112) | asked Oct 20 '16, 11:28 a.m.
 Haw can I link an old task in 'plan A' to a new plan or sprint?

One answer



permanent link
Don Yang (7.7k21114139) | answered Oct 20 '16, 6:42 p.m.
Hi, WIlliam

If Plan A and new plan are in a same project area, drag and drop between plan feature applies:

http://www.ibm.com/support/knowledgecenter/SSYMRC_6.0.0/com.ibm.team.apt.doc/topics/t_modifying_work_items_in_an_iteration_plan.html

Some other discussions may help:
https://jazz.net/forum/questions/159633/how-to-move-work-items-accross-the-plans

There may other similar discussions in Forum depending on the scenarios.