Hi Hani,

The Planned leave and over time data are not available in data warehouse, therefore not available in JRS reports.
Reporting Data Dictionaries
http://www.ibm.com/support/knowledgecenter/SSYMRC_6.0.2/com.ibm.rational.reporting.overview.doc/topics/c_reference_datadictionary.html

Timesheet attributes are available though.
http://www.ibm.com/support/knowledgecenter/SSYMRC_6.0.2/com.ibm.team.reports.doc/topics/ccm/Timesheet.html

There were similar posts on jazz.net
https://jazz.net/forum/questions/69664/viewing-leave-and-availiblity-for-whole-team
Please review those Enhancement requests mentioned in above post to see if that help.
Thanks.
hani zaidi selected this answer as the correct answer

1 vote

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 7,496
× 481
× 360
× 230
× 28

Question asked: Sep 22 '16, 8:54 a.m.

Question was seen: 2,567 times

Last updated: Sep 22 '16, 10:48 p.m.

Confirmation Cancel Confirm