Planned leaves and over time in JRS


hani zaidi (74822) | asked Sep 22 '16, 8:54 a.m.

How to calculate the capacity of a team considering the planned leaves and over time? Can we get Scheduled absences from user details in JRS? Is there any other workaround to get user timesheet attributes in JRS?

I am using CLM V6.0.2 with MSSQL DB

Thanks!

Accepted answer


permanent link
Cathy Xu (390515) | answered Sep 22 '16, 10:48 p.m.
Hi Hani,

The Planned leave and over time data are not available in data warehouse, therefore not available in JRS reports.
Reporting Data Dictionaries
http://www.ibm.com/support/knowledgecenter/SSYMRC_6.0.2/com.ibm.rational.reporting.overview.doc/topics/c_reference_datadictionary.html

Timesheet attributes are available though.
http://www.ibm.com/support/knowledgecenter/SSYMRC_6.0.2/com.ibm.team.reports.doc/topics/ccm/Timesheet.html

There were similar posts on jazz.net
https://jazz.net/forum/questions/69664/viewing-leave-and-availiblity-for-whole-team
Please review those Enhancement requests mentioned in above post to see if that help.
Thanks.
hani zaidi selected this answer as the correct answer