Sprint backlog plan view Roadmap: how are the blocks of time calculated?
Regarding Plans: In the Scrum process template, a Sprint Backlog plan type has the view available of Roadmap. Where can we find more information about the population of the chart? IE: What makes some epics, stories, or tasks appear with a block of time and others not? What goes into that calculation. In help (and here) the only info I found was:
"Roadmap: Displays work items sorted by rank. The Accumulated Time column displays the duration bar for each work item indicating the duration taken to resolve the work item. You can see the Block and Depends on relationship of work items. You can drag the right end of the duration bar to change the estimate of the work item. Rescheduling changes the work sequence as defined in the My Work view."
That does not provide enough clear information.
Thank you for help in advance!
"Roadmap: Displays work items sorted by rank. The Accumulated Time column displays the duration bar for each work item indicating the duration taken to resolve the work item. You can see the Block and Depends on relationship of work items. You can drag the right end of the duration bar to change the estimate of the work item. Rescheduling changes the work sequence as defined in the My Work view."
That does not provide enough clear information.
Thank you for help in advance!
Accepted answer
Please see https://jazz.net/library/article/586 and https://jazz.net/wiki/bin/view/Deployment/RTCProcessFundamentals#Planning_Fundamentals for some minimal information.
I agree, that this could be documented better. My summary from what I have discussed and seen:
A work item gets planned if it has
I agree, that this could be documented better. My summary from what I have discussed and seen:
A work item gets planned if it has
- An owner that has scheduled availability for the owner of the plan (process area)
- Is planned for an iteration (would not show up in the plan otherwise either)
The time shown in the box depends on the availability of the person at that time (e.g. person available 30% and one day effort -> 3 days duration in plan). Person on scheduled absence can add days.
The order of the items (for an owner) correspond to the order in the Eclipse Client MyWork view. You can drag and drop in the roadmap, but I found that not very effective.
Comments
Lily Wang
Sep 20 '16, 9:12 p.m.Donna Thomas
Sep 19 '16, 1:11 p.m.Lily Wang
Sep 19 '16, 9:14 p.m.Donna Thomas
Sep 20 '16, 8:48 a.m.Lily Wang
Sep 20 '16, 9:12 p.m.