Roadmap View
Can anyone explain how RTC (web client) determines the length/time for each "bar" associated with a task in the Roadmap view? Currently I have a release backlog that spans from 11/20/12-6/30/12. I enter a user story on 12/4 with two tasks, both estimated to take 1 hour. The "bar" for the first task spans from 12/4-12/12. The "bar" for the second task spans from 12/12-12/20. I can't figure out how a each task is spanning a week when the estimate is an hour. If I change an estimate to 4 hours, the "bar" then spans a month? If anything I would expect these "bars" to span a single day.
|
Accepted answer
The bar associated with the task determines the duration for which the task has to be executed. It depends on the following parameters:
Kris Laughrey selected this answer as the correct answer
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.