Is there a way to create work items in a team area and not affect the burn down chart for other items already used by another team?

I am trying to create work items in an already existing team area, but I don't want to affect the burn down chart of the already existing team. 

0 votes



One answer

Permanent link
Please read https://jazz.net/wiki/bin/view/Deployment/RTCProcessFundamentals to understand the basics.
Burn down and burn up look for the work items for a team planned for a specific iteration. So if you enter work items they only appear based on filed against and planned for. If you pick the backlog for planned for for example you should be fine.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,019

Question asked: Aug 05 '16, 11:40 a.m.

Question was seen: 1,965 times

Last updated: Aug 08 '16, 2:34 a.m.

Confirmation Cancel Confirm