Is it possible to compare attribute values to colorize work items in plans?
I created a release plan in RTC 5.0.2 and applying adjustments to the view editor work breakdown and scheduling. I'm having trouble with the color feature. I need to colorize items in plan whose time spent is higher than the estimated time. I tried to use timeSpent>estimate but did not work.
One answer
I don't think you can do it that way. The hint actually gives you an idea what you can do with a particular attribute. For example, for both "estimate" and "timespent", you only get a semicolon like "estimate: " and "timespent: ". This means that you can only use "equal", but not "great than" or "less than".