Multiple planned for in a signle work item - RTC 6.0.1
Hi,
As a PO i would like to plan my epics in a release plan. I need to do some forecast here.
I have an epic which I forecast & estimate it would take 3 sprints to be delivered.
Does RTC allow to select more than one 'Planned for' value ? So that in my release plan (Schedule variance view) , the bars are displayed accordingly for 3 sprint dates .
Is this possible in RTC? to be able to assign multiple values for 'Planned for' attribute ?
Thanks,
Praveen
One answer
Typically what you would do is build an iteration hierarchy that has all the sprints you planned to do for this release.
then when u build the release plan, you select the release level iteration. epics get assigned to the release iteration, storys to the sprint iterations.
story = work that gets done in one iteration
epic = work that requires multiple iterations to complete
theme = work that requires multiple epics to complete.
then when u build the release plan, you select the release level iteration. epics get assigned to the release iteration, storys to the sprint iterations.
story = work that gets done in one iteration
epic = work that requires multiple iterations to complete
theme = work that requires multiple epics to complete.