It's all about the answers!

Ask a question

RTC plan view Burndown progress with applied filters (Ex:Team wise)


Balaji KM (11) | asked Jan 05 '23, 11:52 p.m.

 I have  a plan view and am able to see the burndown chart displaying correctly for the particular scrum team.



In plan view for sprint, Lets say, total hours includes all team members : 160 hrs  for 2 team members for 2 weeks  and burndown chart shows the data correctly

Not am filtered one resource and total hours reduced to 80 hours , but the burndown chart in the plan view shows still 160 hrs as total, how to fix this issue ?

One answer



permanent link
Ralph Schoon (63.1k33646) | answered Jan 06 '23, 4:06 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

 For all I know, just because you filter out work items for a team member or other criteria, does not change the team allocation, so the plan would only show the data not filtered out, but the aggregated data based on the team allocation would not change. So what you see is  what should be expected, for all I can tell.

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.