change Test Case Estimation attribute
One answer
The day/time duration widget for the Estimate in the test case editor is a predefined widget that can not be customized.
Comments
Just wondering Yossi, is any of the day and time units not appropriate? We can better assist if you add some more detail.
- Paul -
Hi Paul,
I can share with you more details.
Our customer needs to manage the following data.
The test are executed on simulators (execution machine).
The customer would like to record for each test case how many shifts (and not hours) are estimated for each test case.
Example: 1 shift is 8 hours. The customer would like to indicate : test case= 2 shifts (and not 16 hours).
As a solution we can add new custom attribute, but the problem is that currently it will not be inherited from the planning (test case) to TCER. (like "estimate" attribute).