How do I write Parent & Child Test Cases in RQM

Scenario :
I can execute test case 1 , only after executing Test case 1a,1b,1c.(Precondition).
Is this achievable in RQM ?

0 votes


Accepted answer

Permanent link
There is no such out of the box precondition.
However, you may add a condition to execute the test cases only if approved.
test case 1 can still be in draft and 1a 1b and 1c in approved state.
This way the lead has the option to approve test case 1only after he has the results from test case 1a 1b and 1c.

Hope this helps!!

Best Regards
Rajat
Girish Chandra P selected this answer as the correct answer

0 votes

Comments

Dear Rajat,

Thanks for the answer.

Regards

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,015

Question asked: Jul 18 '13, 3:01 a.m.

Question was seen: 5,549 times

Last updated: Jul 24 '13, 5:28 a.m.

Confirmation Cancel Confirm