Quick Planner: Move Parent / Child workitems in one step
We are using the quick planner to move workitems from the Backlog to a specific Program Increment.
If I move the parent then the children stories were not moved. Is there a way to move all children and the parent in one step to the another iteration ? |
Accepted answer
Katrin,
The ability to perform multi-select and bulk update from quick planner was introduced in 6.0.1. https://jazz.net/downloads/rational-team-concert/releases/6.0.1?p=news (search for "bulk edit" to find the relevant section) Shawn Katrin Heymann selected this answer as the correct answer
|