Where do we set up Iteration type in Test case execution record?
Where do we set up Iteration values in Test case execution record Summary?
Screen print below |
Accepted answer
You have to set up a Timeline under Manage project timelines under the drop down Gear in upper right of screen. Then you add the time line to your test schedule in the test plan. You can set up multiple iteration schedules say for each release and then choose the one to apply to the test plan - this will pull in all the sub levels that are part of the iteration top level. Then when you go to create TERs you will see the iteration values on the left side of the Generate TER panel. You can multi-select values so you can create duplicate TERs for different iterations for example you might have regression TERs that you want to run through out the release.
Aparna Sukumaran selected this answer as the correct answer
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.