Hi Team,

I need to add one more line in drop down menu of planned for (Iteration), now its 2015 and i want to add new one is 2016.
Please suggest me how to edit.

Thanks & Regards

One answer



permanent link
Ralph Schoon (63.6k33647) | answered Feb 05 '16, 5:51 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
You basically have to go into the project administration and add new iterations to the timeline.