Requirements View - Validated By Link. Wanting to see test result.
We are using RRC/CLM 4.0.4
I am trying to create a view of Requirements by Project phase and would also like to show compliance status from test result.
In the MODULE view, If I include the "Validated by" Link i can see on screen - the green/red status of the test result. But if I use the "Create and Print" option. I get the test case link but not the test result.
Is there any way to get a printed report of the Traceability from a Requirement to a Test Case and to the test case result?
I am trying to create a view of Requirements by Project phase and would also like to show compliance status from test result.
In the MODULE view, If I include the "Validated by" Link i can see on screen - the green/red status of the test result. But if I use the "Create and Print" option. I get the test case link but not the test result.
Is there any way to get a printed report of the Traceability from a Requirement to a Test Case and to the test case result?
Accepted answer
Hi Tony,
You can use the OOTB reports included in RQM (Reports -> Shared Reports -> Requirements). "Plan Requirements Execution using TCER Count" will show the requirements per execution result. "Requirements Traceability" will show the requirements and the Test Case/Test Plan linked to them. "Plan Requirements Coverage Detail" will show the Test Plan, Requirement and Test Cases linked.
If none of these OOTB reports work for you and you have RRDI, you can also create your own report there. The information you will need to link is included on each area per artifact (e.g. Test Plan Area, Test Case Area, etc.)
Thank you,
Clara F.
You can use the OOTB reports included in RQM (Reports -> Shared Reports -> Requirements). "Plan Requirements Execution using TCER Count" will show the requirements per execution result. "Requirements Traceability" will show the requirements and the Test Case/Test Plan linked to them. "Plan Requirements Coverage Detail" will show the Test Plan, Requirement and Test Cases linked.
If none of these OOTB reports work for you and you have RRDI, you can also create your own report there. The information you will need to link is included on each area per artifact (e.g. Test Plan Area, Test Case Area, etc.)
Thank you,
Clara F.