CLM 502.

All, we have 502 on server1. We want to update the UAT server (server2) with the latest data from production. I have been given ONE additional machine to install JRS on. Can it connect to both the production and UAT machines?

0 votes


Accepted answer

Permanent link
 Hello Mahari,

I'm not sure I fully understand... Are you wondering if a deployment of JRS can attach to both a staging deployment of CLM DW and a production deployment DW of CLM?  If this is what you're asking - yes it can.  As a report manager you would navigate to the Data sources tab and manually add a new data source for either the production or staging DW (depending on where JRS is installed).  As long as you know the Data Warehouse password for the functional user you can do this.

Then during report creation you can select which Data source you want to create the report on - whether it be the Staging or Production DW.

Hope that helps,

-Steve
Mahari Hill selected this answer as the correct answer

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 7,495
× 6,121
× 360

Question asked: Jan 19 '16, 11:48 a.m.

Question was seen: 3,088 times

Last updated: Jan 19 '16, 7:15 p.m.

Confirmation Cancel Confirm