Resource zero percent allocation
Usman Tahir (27●2●8)
| asked Nov 15 '15, 4:20 a.m.
edited Nov 18 '15, 12:22 a.m. by Don Yang (7.7k●21●114●139)
I am facing a similar situation in which I have a 'dummy project' and top level for a department. A resource can or cannot have a work task assigned, so primarily should be 0% allocated to this project. The hurdle is that if I confirm the 100% allocation on other projects and a short task (lets say for few hours) at dept level come up, I cannot readjust all project allocations automatically. Is there a way to do it?
I primarily was going through following question: ' Resource allocation when adding a team member is not zero?!'
not sure how the site works if I have to ask a linked question. Hope I have clarified my query; if not please feel free to ask.
|
Be the first one to answer this question!
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.