Can scrum master update scheduled absences for update hours for the entire team?
![](http://jazz.net/_images/myphoto/550b993338e2cdedd495b5abb74fb9fc.jpg)
One answer
![](http://jazz.net/_images/myphoto/550b993338e2cdedd495b5abb74fb9fc.jpg)
There isn't any Work Environment configuration at the team level. The scheduled absences are only at the user level, but available hours can also be updated at the project level.
See Eclipse Work Environment in:
https://jazz.net/help-dev/clm/index.jsp?re=1&topic=/com.ibm.jazz.platform.doc/topics/t_set_work_hours.html&scope=null