Set Customer Work Item Type As Plan Item
How do I set a custom work item type to be a Plan item?
I created a custom work item type and I want to update this from being an execution item to a plan item. When I exclude execution items in my plan view the custom type is excluded and I do not want that to happen. I can not see any option in the ''Manage Project Area' to set this custom work item type to be a Plan item. Thanks, Andy. |
Accepted answer
Hi Andrew, To set the work Item to a Plan Item: In Eclipse: Process Configuration tab > Configuration Data > Planning > Work Item Type Categorization. I hope that helps: Matt Muller
Andrew Morrison selected this answer as the correct answer
Comments
Andrew Morrison
commented Nov 24 '15, 8:20 a.m.
Thanks Matt.
|