Set Customer Work Item Type As Plan Item


Andrew Morrison (155) | asked Nov 24 '15, 6:54 a.m.
edited Nov 24 '15, 8:20 a.m.
How do I set a custom work item type to be a Plan item?

I created a custom work item type and I want to update this from being an execution item to a plan item.

When I exclude execution items in my plan view the custom type is excluded and I do not want that to happen.

I can not see any option in the ''Manage Project Area' to set this custom work item type to be a Plan item.

Thanks,
Andy.

Accepted answer


permanent link
Matt Muller (58312462) | answered Nov 24 '15, 7:10 a.m.

Hi Andrew,

To set the work Item to a Plan Item:

In Eclipse:  Process Configuration tab > Configuration Data > Planning > Work Item Type Categorization.

I hope that helps:

Matt Muller

Andrew Morrison selected this answer as the correct answer

Comments
Andrew Morrison commented Nov 24 '15, 8:20 a.m.

Thanks Matt.

I had been searching in the Web UI without success, but your advice via Eclipse is exactly what I was looking for.

cheers
Andy.