How do I set a custom work item type to be a Plan item?

I created a custom work item type and I want to update this from being an execution item to a plan item.

When I exclude execution items in my plan view the custom type is excluded and I do not want that to happen.

I can not see any option in the ''Manage Project Area' to set this custom work item type to be a Plan item.

Thanks,
Andy.

Accepted answer


permanent link
Matt Muller (59813274) | answered Nov 24 '15, 7:10 a.m.

Hi Andrew,

To set the work Item to a Plan Item:

In Eclipse:  Process Configuration tab > Configuration Data > Planning > Work Item Type Categorization.

I hope that helps:

Matt Muller

Andrew Morrison selected this answer as the correct answer

Comments
Andrew Morrison commented Nov 24 '15, 8:20 a.m.

Thanks Matt.

I had been searching in the Web UI without success, but your advice via Eclipse is exactly what I was looking for.

cheers
Andy.

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.