On RQM when exporting Test Plan into pdf Risks/Risks actions are mixing up, how to fix it?
Hi,
on RTC we have:
Insufficient test resources --> mitigation Action 2 Inexperienced team --> mitigation Action 3 on PDF export we see: Insufficient test resources --> mitigation Action 1 Inexperienced team --> mitigation Action 2 Insufficient developer test --> mitigation Action 3
Regards |
One answer
Comments
Lorena Almela
commented Jun 15 '15, 11:33 a.m.
Hi Paul, thanks for your answer. I've just created the Defect Risks / Risks actions are mixing up on PDF Export (138389) as I found no other similar defect or post related to this issue. Regards, |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.