It's all about the answers!

Ask a question

On RQM when exporting Test Plan into pdf Risks/Risks actions are mixing up, how to fix it?


Lorena Almela (1811617) | asked Jun 12 '15, 1:25 p.m.

Hi,
we are using RQM 4.0.6. While exporting a test Plan into pdf the Risks are mixing up, showing in different order and so mixing up the mitigation actions:

on RTC we have:
 
Insufficient developer test --> mitigation Action 1

Insufficient test resources --> mitigation Action 2

Inexperienced team --> mitigation Action 3

on PDF export we see:

Insufficient test resources --> mitigation Action 1

Inexperienced team --> mitigation Action 2

Insufficient developer test --> mitigation Action 3


has anyone faced this issue? Is there any fix?

Regards

One answer



permanent link
Paul Slauenwhite (8.4k12) | answered Jun 15 '15, 11:17 a.m.
FORUM MODERATOR / JAZZ DEVELOPER

Comments
Lorena Almela commented Jun 15 '15, 11:33 a.m.

Hi Paul,

thanks for your answer. I've just created the Defect Risks / Risks actions are mixing up on PDF Export (138389) as I found no other similar defect or post related to this issue.

Regards,

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.