we are using RQM 4.0.6. While exporting a test Plan into pdf the Risks are mixing up, showing in different order and so mixing up the mitigation actions:

on RTC we have:
 
Insufficient developer test --> mitigation Action 1

Insufficient test resources --> mitigation Action 2

Inexperienced team --> mitigation Action 3

on PDF export we see:

Insufficient test resources --> mitigation Action 1

Inexperienced team --> mitigation Action 2

Insufficient developer test --> mitigation Action 3


has anyone faced this issue? Is there any fix?

Regards

One answer



permanent link
Paul Slauenwhite (8.4k12) | answered Jun 15 '15, 11:17 a.m.
FORUM MODERATOR / JAZZ DEVELOPER

Comments
Lorena Almela commented Jun 15 '15, 11:33 a.m.

Hi Paul,

thanks for your answer. I've just created the Defect Risks / Risks actions are mixing up on PDF Export (138389) as I found no other similar defect or post related to this issue.