Is it possible to extract Planned Start Date and Planned End Dates in Reports?
Accepted answer
Hi Sandhya,
The Planned Start Date and Planned End Date are calculated data which are not stored in work item but in plan. Those data are not collected in data warehouse by default.
If you are using BIRT or RRDI report, it's not possible to extrace Planned Start Date and Planned End Date.
There are some similar discussion for your reference:
https://jazz.net/forum/questions/86027/insight-how-to-extract-planned-start-date-and-planned-end-date
https://jazz.net/forum/questions/142596/birt-report-datasourcesnapshottable-for-planned-start-and-end-date-in-formal-project-planning
The Planned Start Date and Planned End Date are calculated data which are not stored in work item but in plan. Those data are not collected in data warehouse by default.
If you are using BIRT or RRDI report, it's not possible to extrace Planned Start Date and Planned End Date.
There are some similar discussion for your reference:
https://jazz.net/forum/questions/86027/insight-how-to-extract-planned-start-date-and-planned-end-date
https://jazz.net/forum/questions/142596/birt-report-datasourcesnapshottable-for-planned-start-and-end-date-in-formal-project-planning