How to get cross project report for Effort estimate and Progress?
![]()
Shuchita Tripathi (314●3●57●93)
| asked Apr 13 '15, 6:36 a.m.
edited Apr 13 '15, 10:14 a.m. by Ralph Schoon (62.7k●3●36●43)
Hi,
The scenario is:
I have multiple tasks in multiple work items. I want to see a parent work item, which links all the tasks from multiple project area and gives me the total effort and total progress by calculating from all child tasks.
I created a cross project plan for this, but the effort estimate and progress of the tasks which are in different project is not getting reflected. I have added associations in project area.
How can I achieve total effort estimate and total progress of all child tasks at one place?
|
One answer
![]()
Can be achieved using RRDI.
https://jazz.net/forum/questions/178669/how-to-get-a-report-for-sum-of-time-estimated-for-all-work-items-for-each-user-in-rtc
|