Create Parent child relationship between project areas in Rational CLM
One answer
Hi Swapna, as Ralph mentioned, there is no parent/child relationship between project areas in RTC which is similar to the parent/child relationships in work items.
There is process sharing, which allows one process to be the Master, and all projects underneath inherit the process configuration. This is different from the parent/child relationship in work items as well.
I know you mentioned you didn't want to configure team areas, but this is probably the best option to mimic the parent/child relationship from work items into a project area context.
There is process sharing, which allows one process to be the Master, and all projects underneath inherit the process configuration. This is different from the parent/child relationship in work items as well.
I know you mentioned you didn't want to configure team areas, but this is probably the best option to mimic the parent/child relationship from work items into a project area context.
Comments
Ralph Schoon
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER Feb 04 '15, 6:25 a.m.1 vote
Ralph Schoon
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER Feb 04 '15, 6:27 a.m.1 vote
swapna das
Feb 05 '15, 5:48 a.m.Ralph Schoon
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER Feb 05 '15, 7:10 a.m.