How to represent 2 parallel tasks in the Roadmap plan view
![]()
A developer works on 2 tasks parallely.
Roapmap view shows Task 1 & Task 2 sequentially, i.e., Task 2 starts after Task 1 completes. How to represent 2 parallel tasks in the Roadmap view. |
Accepted answer
![]()
Ralph Schoon (61.8k●3●36●43)
| answered Jan 07 '15, 7:15 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Parallel tasks are not supported. they will, at best, only show as "parallel", as soon as the user has both moved out of the new state into an in progress state as far as I know.
Chidambaram L selected this answer as the correct answer
|