A developer works on 2 tasks parallely.
Roapmap view shows Task 1 & Task 2 sequentially, i.e., Task 2 starts after Task 1 completes.
How to represent 2 parallel tasks in the Roadmap view.

1 vote


Accepted answer

Permanent link
Parallel tasks are not supported. they will, at best, only show as "parallel", as soon as the user has both moved out of the new state into an in progress state as far as I know.
Chidambaram L selected this answer as the correct answer

1 vote

Comments

Yes. That is one way to interpret Parallel tasks.

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,224

Question asked: Jan 06 '15, 6:54 a.m.

Question was seen: 3,731 times

Last updated: Jan 07 '15, 8:05 a.m.

Confirmation Cancel Confirm