It's all about the answers!

Ask a question

Sharing timelines between RTC and RQM


Brent Reid (812) | asked Dec 12 '14, 12:23 p.m.

I know there have been some discussions on sharing timelines between RTC and RQM. Is there anyway to share the timeline between the Rational Team Concert planning system with the Rational Quality Manager (RQM)?

If there is not, what are lessons learned or recommendations on how to keep the timeline in RTC "synchronized " with the timeline in RQM?

Please provide guidance. We are new to both RTC and RQM and we are finding it to be a challenge to get things setup for our project. We are currently using RTC 4.0.6.

Accepted answer


permanent link
Geoffrey Clemm (30.1k33035) | answered Dec 12 '14, 5:45 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
The only approach I'm aware of is to use the RTC and RQM API's to generate/update the two timelines.   If you decide to take that approach, and need some guidance on how to use the API's, we'd need someone else from the forum to provide that guidance.
Brent Reid selected this answer as the correct answer

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.