Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

Is it possible to link a RTC project in a repository at v6.0.1 to a RQM project in repository at v4.0.3

We have a RTC project in a repository (JTS and RTC version 5.0.2) linked to RQM projects in repository (JTS and RQM version 4.0.3).

We are looking to upgrade the first repository with the RTC project to v6.0.1. We are trying to determine if the repository containing the RQM project can remain at 4.0.3 for the time being. I have not seen any guidance on this in the research I did so far.

0 votes

Comments

How are the projects in RTC and RQM linked together? Could you please explain?

The defects in RTC project would be linked to RQM work items with a  "is tested by test case" link. I linked the projects across repositories not by creating a lifecycle project but manually following instructions in the link below (skip step 2 for lifecycle project)

https://www-01.ibm.com/support/knowledgecenter/SSCP65_5.0.1/com.ibm.rational.test.qm.doc/topics/t_config_rtc_defects_overview.html



One answer

Permanent link
Hi. The bottom line is no. We support n-1 version compatibility. RTC 6.x can integrate with RQM 5.x but not 4.x.

In your scenario if RTC is coming from 4.x you will need to upgrade to 5.x and then 6.x. It is not possible to directly migrate from 4.x to 6.x. I'd suggest you move step wise with the migration to maintain compatibility.


0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 6,121

Question asked: Feb 25 '16, 11:12 a.m.

Question was seen: 2,602 times

Last updated: Mar 03 '16, 8:19 a.m.

Confirmation Cancel Confirm