Product Backlog Plan - Progress Bar data
I have a Product Backlog Plan with a number of work items within. None have Story Points and the majority do not have estimates. Those that do have estimates, total 16371 hours. Within the Plan progress bar, the values are shown as;
Progress: 2735999998/21819599913 Estimate
Estimated: 40%
Progress: 0/0 h
Estimated: 96%
Where are the figures of 2735999998 and 21819599913 coming from? I've read the https://jazz.net/library/article/586 but that offers me no assistance.
|
One answer
The values are displayed in milliseconds, as a result of 'Estimate' being used as the complexity |