Product Backlog Plan - Progress Bar data


Richard Tweed (811220) | asked Nov 07 '14, 8:54 a.m.

I have a Product Backlog Plan with a number of work items within.  None have Story Points and the majority do not have estimates.  Those that do have estimates, total 16371 hours.

Within the Plan progress bar, the values are shown as;

Progress: 2735999998/21819599913 Estimate
Estimated: 40%
Progress: 0/0 h
Estimated: 96%
Where are the figures of 2735999998 and 21819599913 coming from?  I've read the https://jazz.net/library/article/586 but that offers me no assistance.

One answer



permanent link
Richard Tweed (811220) | answered Nov 13 '14, 5:49 a.m.
edited Nov 13 '14, 5:49 a.m.

https://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=267706

The values are displayed in milliseconds, as a result of 'Estimate' being used as the complexity